None

Recent plan failures

Failed In Fixed In Time Taken To Fix
#35 Changes by 3 people

#37 Changes by Graham Mann <graham.mann@bilney.co.uk>

2 builds

2 weeks, 14 hours, 31 minutes

#17 Manual run by Rainer Prosi

#19 Manual run by Rainer Prosi

2 builds

5 days, 22 hours, 18 minutes

#14 Rebuilt by Rainer Prosi

#15 Manual run by Rainer Prosi

1 build

2 weeks, 4 days, 15 hours, 49 minutes

  • Average time to fix a failure: 1 week, 6 days, 1 hour, 33 minutes
  • Average number of builds between fixes: 1.67 builds
  • The longest time taken to fix a failure is 2 weeks, 4 days, 15 hours, 49 minutes, from failure starting in build #14.
  • The greatest number of builds taken to fix a failure is 2, from failure starting in build #17.